If you’re planning construction work that affects shared walls or structures with your neighbours, you’ll likely need to serve a party structure notice. This formal document is a legal requirement under the Party Wall etc. Act 1996 and helps prevent disputes between property owners. Understanding when and how to serve this notice correctly can save you from delays, legal complications, and damaged relationships with your neighbours.
In this comprehensive guide, we’ll walk you through everything you need to know about party structure notices – from what they are and when they’re required to how to draft them correctly and what happens after they’re served. We’ll also provide real-world examples and a usable template to help you navigate this often complex process.
What Is a Party Structure Notice?
A party structure notice is a formal legal document served by a building owner to adjoining owners when planning construction work that affects shared structures. Under the Party Wall etc. Act 1996, this notice must be given before commencing certain types of work that might impact party walls, party structures, or party fence walls.
A party structure specifically refers to a wall or floor that separates buildings or parts of buildings belonging to different owners. This includes walls that form part of only one building but separate parts owned by different people, such as in apartment buildings or semi-detached houses.
The notice serves as an official communication informing neighbours about your planned works and gives them the opportunity to consent or dissent to the proposals. It’s an essential step in the party wall process and helps establish clear communication between property owners from the outset.
Party Structure Notice vs. Party Wall Notice
While often used interchangeably, there is a technical difference between a party structure notice and a party wall notice:
Notice Type | Applies To | Legal Reference |
Party Structure Notice | Works on existing party walls, party structures, or party fence walls | Section 3 of the Party Wall etc. Act 1996 |
Line of Junction Notice | Building a new wall up to or astride the boundary line | Section 1 of the Party Wall etc. Act 1996 |
Adjacent Excavation Notice | Excavation within 3-6 metres of neighbouring structures | Section 6 of the Party Wall etc. Act 1996 |
For the purposes of this guide, we’ll focus primarily on party structure notices, though many of the principles apply to all types of notices under the Act.
When Must a Party Structure Notice Be Served?
Under the Party Wall etc. Act 1996, you must serve a party structure notice at least two months before commencing any work that falls under Section 3 of the Act. This includes various types of construction that affect existing party structures.
Types of Work Requiring a Party Structure Notice
You’ll need to serve a party structure notice if you plan to:
- Cut into a party wall to insert beams, flashings, or damp proof courses
- Raise the height of a party wall or increase its thickness
- Demolish and rebuild a party wall
- Cut off projections from a party wall (like chimney breasts)
- Underpin a party wall
- Expose a party wall by excavating below the level of its foundation
- Cut away from a party wall
It’s important to note that the Act defines a party structure broadly. It includes party walls (walls shared between properties), party fence walls (free-standing walls at boundaries), and floors/ceilings between flats.
Timing Requirements
The timing requirements for serving notices are strict:
Notice Type | Minimum Notice Period | Response Deadline |
Party Structure Notice | 2 months before work begins | 14 days for adjoining owner to respond |
Failing to serve notice or not allowing sufficient time can result in legal action, including an injunction to stop your work and potential claims for damages.
5 Essential Elements Every Valid Party Structure Notice Must Include
For a party structure notice to be legally valid, it must contain specific information. Missing or incorrect details can invalidate your notice, causing delays and complications. Here are the five essential elements every party structure notice must include:
1. Building Owner’s Details
The notice must clearly state the name and address of all building owners (those carrying out the work). If the property is jointly owned, all owners must be named and sign the notice. This establishes who is legally responsible for the proposed works.
2. Detailed Description of Proposed Works
Your notice must include a comprehensive description of all planned works that affect the party structure. This should be specific enough that your neighbour can understand exactly what you intend to do. Vague descriptions like “renovation work” are insufficient.
Include details such as:
- The exact location of the work on the party structure
- The nature and extent of the work
- Any temporary support measures that will be needed
- How the work will be carried out
It’s often helpful to include drawings or plans to clarify your intentions.
3. Proposed Start Date
The notice must specify when you intend to begin the work. Remember that for party structure notices, you must allow at least two months between serving the notice and starting work. This gives your neighbour time to consider your proposals and, if necessary, for surveyors to be appointed and prepare a party wall award.
4. Date of Service
The notice must be dated with the day it is served to the adjoining owner. This is crucial for calculating the 14-day response period and the two-month notice period before work can begin.
5. Signature of Building Owner(s)
All building owners must sign the notice. Without proper signatures, the notice is not legally valid. Digital signatures are generally acceptable, but physical signatures are preferable to avoid any disputes about authenticity.
Additional Helpful Elements: While not strictly required by law, including the following can help prevent misunderstandings:
- Contact information for quick communication
- Information about the Party Wall etc. Act 1996 and your neighbour’s rights
- A response form for your neighbour to indicate consent or dissent
- Details of any party wall surveyor you’ve appointed
Party Structure Notice Template
Below is a template for a party structure notice that includes all the essential elements required by law. You can use this as a starting point, but remember to customize it to your specific situation and proposed works.
Party Structure Notice Template
Date: {DATE}
To: {ADJOINING OWNER NAME/ADDRESS}
Description of works: {ITEMIZED LIST}
Planned start date: {DATE}
Surveyor details: {NAME/CONTACT}
Here’s a more detailed example of how to complete this template:
Party Structure Notice
Served under Section 3 of the Party Wall etc. Act 1996
Date of Service: 15 June 2023
To:
Mr. John Smith
123 Acacia Avenue
London
SW1 2AB
From:
Mrs. Sarah Johnson
125 Acacia Avenue
London
SW1 2AB
Description of Proposed Works:
I am proposing to carry out the following works that will affect the party wall between our properties:
- Cut into the party wall to insert steel beams to support a loft conversion
- Remove the chimney breast on my side of the party wall
- Install a damp proof course in the party wall
Plans and drawings showing these works are attached to this notice.
Proposed Start Date: 20 August 2023
Party Wall Surveyor:
I have appointed Mr. David Williams of Williams Surveying Ltd. (contact: 020 1234 5678, david@williamssurveyingltd.co.uk) to act as my party wall surveyor.
Your Rights:
Under the Party Wall etc. Act 1996, you have 14 days from the date of service of this notice to respond. You may:
- Give your consent to the works
- Dissent to the works and appoint your own surveyor
- Agree to use my surveyor as an “agreed surveyor”
If you do not respond within 14 days, you will be deemed to have dissented and a surveyor will need to be appointed.
Signature: [Signature]
Sarah Johnson
Remember to attach any relevant drawings or plans to help your neighbour understand the proposed works.
How to Properly Serve a Party Structure Notice
Serving a party structure notice correctly is just as important as including the right information. Improper service can invalidate your notice and cause significant delays to your project.
Legal Methods of Service
The Party Wall etc. Act 1996 specifies several methods for serving notices:
- Personal delivery: Handing the notice directly to the adjoining owner
- Leaving it at the person’s usual or last-known residence or place of business
- Sending it by post: Using recorded delivery is recommended to prove service
- If the adjoining owner is not known: Addressing the notice to “the owner” and affixing it to a conspicuous part of the premises
For the most secure method, consider using recorded delivery post or a process server who can provide proof of delivery.
Who Must Be Served
You must serve notice on all adjoining owners affected by your proposed works. This includes:
- Freeholders of adjoining properties
- Leaseholders with leases longer than one year
- If the property is jointly owned, all owners must be served
If you’re unsure who owns an adjoining property, you can check with the Land Registry.
Proof of Service
Always keep evidence that you’ve served the notice correctly:
- For recorded delivery: Keep the receipt and tracking information
- For personal delivery: Consider having a witness or taking a photo
- Keep copies of all notices and when they were served
This evidence can be crucial if there’s a dispute about whether notice was properly served.
Important: The 14-day response period for adjoining owners begins from the day after the notice is served. The two-month notice period before work can begin is calculated from the date of service. Incorrect calculation of these periods can invalidate your notice.
What Happens After Serving a Party Structure Notice
After serving a party structure notice, several scenarios can unfold depending on how your neighbour responds. Understanding these possibilities helps you prepare for the next steps in the process.
Possible Responses from Adjoining Owners
Your neighbour has 14 days to respond to your notice. They can:
Consent
They agree to the proposed works without conditions. This is the simplest outcome, allowing you to proceed once the two-month notice period expires.
Conditional Consent
They agree but with specific conditions. If you accept these conditions, you can proceed without further formalities.
Dissent
They object to the works or don’t respond within 14 days (deemed dissent). This triggers the dispute resolution process.
The Dispute Resolution Process
If your neighbour dissents or doesn’t respond within 14 days, a dispute is deemed to exist under the Act. This doesn’t mean your project can’t proceed, but it does require following a specific process:
- Both parties must appoint a party wall surveyor. You can each appoint your own, or agree on a single “agreed surveyor” to act impartially for both parties.
- The surveyor(s) will inspect both properties and prepare a document called a “party wall award.”
- The award sets out how and when the work should be carried out, including working hours, access arrangements, and protective measures.
- Once the award is served, you can begin work in accordance with its terms (provided the two-month notice period has expired).
The cost of surveyors is typically paid by the building owner (you), although this can be determined differently in the award if appropriate.
Schedule of Condition
Before work begins, it’s advisable to have a “schedule of condition” prepared for the adjoining property. This document records the existing condition of the property with photographs and descriptions, providing a reference point if damage is claimed later.
This is usually prepared by the party wall surveyor and included in the party wall award.
Timeline After Service:
- Day 1-14: Adjoining owner response period
- If consent given: Wait until two-month notice period expires, then begin work
- If dissent or no response: Appoint surveyors, prepare award (typically 4-6 weeks), then begin work after two-month notice period
Consequences of Improper Notice or Failure to Serve
Failing to serve a party structure notice correctly, or not serving one at all, can have serious legal and financial consequences. Understanding these risks highlights the importance of following proper procedures.
Legal Consequences
- Injunctions: Your neighbour can apply to the court for an injunction to stop your work. This can happen even if the work has already started.
- Trespass claims: Working on a party structure without proper notice can constitute trespass, leading to legal action.
- Damage claims: If your work causes damage to your neighbour’s property, they can claim compensation. Without a party wall award in place, you may be in a weaker position to defend against such claims.
Financial Implications
The financial costs of improper notice can be substantial:
Potential Costs of Improper Notice
- Legal fees for defending against injunctions or claims
- Court costs if the case goes to litigation
- Compensation for damage to adjoining property
- Project delays and associated costs
- Costs of remedial work if construction must be modified
- Increased surveyor fees for resolving disputes
These costs often far exceed what you would have spent on proper notices and party wall surveyors from the outset.
Project Delays
Perhaps the most immediate consequence is delay to your project:
- If an injunction is granted, work must stop immediately until the matter is resolved
- Resolving disputes after work has started is typically more complex and time-consuming
- You may need to restart the notice process, adding at least two months to your timeline
Case Example: In a recent London case, a homeowner began loft conversion work without serving proper party structure notices. The neighbour obtained an injunction, stopping work for three months while the dispute was resolved. The homeowner ultimately paid over £15,000 in legal fees, surveyor costs, and compensation – far more than the £1,500-£2,000 a proper party wall process would have cost initially.
3 Real-World Scenarios Requiring Party Structure Notices
To help you understand when party structure notices are required in practice, here are three common scenarios where property owners must serve notices before proceeding with work.
Scenario 1: Loft Conversions Affecting Shared Walls
Loft conversions in semi-detached or terraced houses typically require structural support for the new floor. This often involves inserting steel beams into the party wall.
Why a Notice is Required:
- Cutting into a party wall to insert beams is specifically covered under Section 3 of the Party Wall Act
- The work could affect the structural integrity of the shared wall
- There’s potential for noise, dust, and vibration to affect your neighbour
Key Considerations:
Your notice should include detailed information about the size and position of the beams, how they will be inserted, and any temporary support measures. Engineering drawings are highly recommended.
“When we planned our loft conversion, we didn’t realize we needed to serve a party structure notice for the steel beams. Our surveyor caught this early, and we’re glad he did – our neighbour had concerns about vibration affecting their plasterwork, which we were able to address in the party wall award.”
– Michael T., Homeowner in Manchester
Scenario 2: Basement Excavations Near Boundaries
Basement excavations and extensions are increasingly popular in urban areas where space is limited. These projects often involve digging close to or below the foundations of party walls.
Why a Notice is Required:
- Excavating within 3 meters of a neighbour’s building and below the depth of their foundations requires notice under Section 6 of the Act
- There’s significant risk of structural movement or damage
- The work may require temporary support structures on the adjoining property
Key Considerations:
Basement excavations are among the highest-risk projects under the Party Wall Act. Your notice should include detailed structural engineering plans, method statements, and information about how you’ll protect the adjoining property. Professional involvement is essential.
Basement excavations often require multiple types of notices – a party structure notice for work to the party wall itself, and an adjacent excavation notice for the digging work. Make sure your notices cover all aspects of the project.
Scenario 3: Chimney Breast Removals
Removing a chimney breast to create more space is common in period properties. Since chimney breasts often form part of party walls in terraced and semi-detached houses, this work requires careful consideration.
Why a Notice is Required:
- Cutting away from a party wall is covered under Section 3 of the Act
- The work affects a shared structure that may support your neighbour’s chimney breast
- Improper removal can cause structural issues and damage to both properties
Key Considerations:
Your notice should detail how the remaining chimney stack will be supported, particularly if your neighbour’s chimney breast remains in place. Structural calculations and drawings are typically required.
“We removed our chimney breast without serving notice, assuming it was entirely on our side. Six months later, cracks appeared in our neighbour’s living room where their chimney breast connected to the party wall. We ended up paying for repairs and retrospective party wall awards – a costly mistake.”
– Sarah L., Homeowner in Bristol
Frequently Asked Questions About Party Structure Notices
What is the response deadline for adjoining owners after receiving a party structure notice?
Adjoining owners have 14 days from the day after service to respond to a party structure notice. They can consent to the works, dissent (object), or request additional information. If they don’t respond within 14 days, they are automatically deemed to have dissented, and the dispute resolution process must be followed.
What are my options if my neighbour disputes my party structure notice?
If your neighbour disputes your notice, you have several options:
- Negotiation: Try to address their concerns directly
- Agreed Surveyor: Appoint a single surveyor to act impartially for both parties
- Separate Surveyors: Each party appoints their own surveyor, who then select a third surveyor as a backup
The surveyor(s) will prepare a party wall award that sets out how the work should proceed. This is legally binding unless appealed to the County Court within 14 days.
What’s the difference between a party wall notice and a party structure notice?
“Party wall notice” is often used as a general term for all notices under the Party Wall etc. Act 1996. Technically, a party structure notice specifically refers to notices served under Section 3 of the Act for work on existing party walls or structures.
Other types of notices under the Act include:
- Line of Junction Notice (Section 1) – for building on the boundary line
- Adjacent Excavation Notice (Section 6) – for excavation near neighbouring structures
The requirements and response periods vary slightly between these notice types.
Can I serve a party structure notice myself, or do I need a surveyor?
You can legally serve a party structure notice yourself without professional help. However, many property owners choose to engage a party wall surveyor to prepare and serve notices because:
- They ensure all legal requirements are met
- They can help address technical questions from neighbours
- If a dispute arises, you’ll need a surveyor anyway
- Incorrect notices can cause significant delays and costs
For simple projects with cooperative neighbours, self-service may be appropriate. For complex work or where disputes are likely, professional assistance is recommended.
How much does the party wall process typically cost?
Costs vary depending on the complexity of the work and whether there are disputes:
- Preparing and serving notices: £75-£150 if done by a surveyor
- Agreed surveyor (if neighbour consents to one surveyor): £800-£1,500
- Two surveyors (if each party appoints their own): £1,500-£3,000+
- Complex projects or disputes: £3,000-£10,000+
The building owner (the person doing the work) typically pays all surveyor costs, although this can be determined differently in the award in certain circumstances.
What happens if I start work without serving a required party structure notice?
Starting work without serving a required notice is risky and can lead to:
- Your neighbour obtaining a court injunction to stop the work
- Legal claims for trespass
- Difficulty defending against damage claims
- Having to serve retrospective notices and potentially undo work already completed
- Significantly higher costs than following the proper process
If you’ve already started work without notice, you should stop immediately and seek professional advice from a party wall surveyor.
Conclusion: Ensuring Compliance and Protecting Your Interests
Navigating the party structure notice process correctly is essential for any property owner planning construction work that affects shared walls or structures. By understanding when notices are required, what they must contain, and how to serve them properly, you can avoid costly disputes, delays, and legal complications.
Remember these key points:
- Serve party structure notices at least two months before starting work
- Include all required information and be specific about your proposed works
- Use proper methods of service and keep evidence
- Be prepared for the dispute resolution process if your neighbour dissents
- Consider engaging a professional party wall surveyor, especially for complex projects
The party wall process may seem bureaucratic, but it serves an important purpose: protecting both your interests and your neighbour’s while facilitating necessary construction work. Taking the time to get it right from the start will save you time, money, and stress in the long run.
Need Professional Help With Your Party Structure Notice?
Our experienced party wall surveyors can help you navigate the entire process – from preparing and serving notices to resolving disputes and preparing party wall awards. Contact us today for a free initial consultation.